REAM Projects in Kirinyaga District (Mt. Kenya):

Since the completion of its Thiba pilot project in 2005 Gpower has launched the construction of 11 further micro-hydro plants in Kirinyaga alone. These 11 projects together make up the first Rural Energy Access Model. In 2008 the Lake Basin Development Authority invited Gpower to replicate another REAM in Western and Nyanza District (Kenya).
 
   
Table 1 shows the 11 communities in central Kenya with whom Gpower is currently engaged to complete it's first REAM. Gpower expects to complete the first 80Kwatt turbine for Kiangurwe before mid 2009. As shown in the table, funding is secured for turbines in 4 neighbouring communities:  
   
Summary Details 1ST Phase Generation 1st Phase Distribution
Project Mw Potential Feasibility Study Construction Completed (%) Secured Funds Feasibility Study Construction Completed(%) Secured Funds
Kiangurwe 0.3 Completed 90 100% Completed 10 10% and sourcing
Riakaruria 0.5 Completed 40 100% Completed 0 sourcing
Inanjugu 0.3 Completed 80 100% Completed 0 sourcing
Rianjue 0.3 Completed 30 100% Completed 0 sourcing
Gitii 0.3 Completed 30 30% Completed - -
Kii 0.08 Completed 60 60% Undertaking - -
Muchungwa 0.5 Completed 20 20% Undertaking - -
Muketura 0.06 Completed 60 100% Undertaking 0 sourcing
Muromu 0.2 Completed 10 10% Undertaking - -
Urumandi 0.2 Completed 10 10% Undertaking - -
Riagiceru 0.2 Completed 10 10% Undertaking - -
 
 
Top  
   

Project Costs:

Table 2 shows the estimated project costs for the 11 generation and distribution facilities.
Project Costs (USD x 1000) in Kirinyaga District, Kenya:

 
   
Project 1st Phase Generation ($) 1st Phase Distribution ($)
Prime Struct. Turbine + Penst. Total Gener. Total Secured No. HH Connect. No. Transform. Total Distrib. Total Secured
Kiangurwe
(100 KW Turbine)
147,140 83,870 231,010 100% 1000 14 587,650 10% ; sourcing for 90%
Riakaruria
(100 KW Turbine)
220,710 83,870 304,590 100% 1000 11 533,688 sourcing
Inanjugu
(100 KW Turbine)
147,140 83,870 231,010 100% 1000 11 533,688 sourcing
Rianjue
(100 KW Turbine)
323,710 83,870 407,590 100% 1000 11 533,688 sourcing
Muketura
(60 KW Turbine)
88,290 83,870 172,160 100% 500 5 269,279 sourcing
Gitii
(100 KW Turbine)
147,140 83,870 231,010 30% 1000 10 515,701 -
Kii
(100 KW Turbine)
88,290 83,870 172,160 60% 500 5 269,279 -
Muchungwa
(100 KW Turbine)
220,710 83,870 304,590 20% 1000 10 533,688 -
Muromu
(100 KW Turbine)
110,360 83,870 194,230 10% 1000 10 515,701 -
Urumandi (100 KW Turbine) 117,710 83,870 201,590 10% 1000 11 533,688 -
Riagiceru (100 KW Turbine) 264,860 83,870 348,730 10% 1000 10 515,701
 
 
Top  
 

Funding Partners:

Table 3 below highlights all the partners that have provided (will be providing) financial support to the different projects.
Funding partners and community support in Kirinyaga District, Kenya:

 
   
Project Household Connections Funding Partners
Kiangurwe 1000 Community Contributions/ TARDA/ Liberty Foundation/ French Embassy
Riakaruria 1000 Community Contributions/ Finnish Emabassy
Inanjugu 1000 Community Contributions/ Africa Lighting
Rianjue 1000 Community Contributions/ Africa Lighting
Gitii 1000 Community Contributions/ Gpower Ltd.
Kii 500 Community Contributions/ Gpower Ltd.
Muchungwa 1000 Community Contributions/ Gpower Ltd.
Muketura 500 Community Contributions/ Japanese Embassy/ Gpower Ltd.
Muromu 1000 Community Contributions/ CDF
Urumandi 1000 Community Contributions/ CDF/ Gpower Ltd.
Riagiceru 1000 Community Contributions/ Gpower Ltd.
 
   